Work on our access project is coming along well. Much work has been achieved but a lot of that work is underground!
The waste and water pipes for the new toilet have been laid and are ready to go.
The groundwork for the ramp and steps has been done and is waiting for the bespoke handrails, which have been fitted and are off being galvanised. The handmade flint wall has been made and fits beautifully with the church building.
Internally the walls for the toilet are up and some damp plaster has been removed and the sunshine is helping the walls to dry well, all the pipework and electrics for the toilet are in and ready to go.
The work is on schedule but has not followed the schedule provided before starting. This means the church and car park are likely to be out of action for a bit longer.