Mind the gap

News_about_our_building

End of week 8 - tower back gutter structure and lead lining complete; eaves timberwork and rafter repairs complete; felt and battens complete; tiling 95% complete; re-ridging 95% complete.

Despite some poor weather, progress has been good. Outstanding work includes the completion of the nave and tower flashings, and refixing rainwater goods.

We're nearly there..