The Scaffolding is complete on the South side.
All metal drainage work has been ordered and delivery expected 12/02 and work on site to start 13/02
Investigations have taken place now that the roof scaffolding is in place which identified some issues but a workaround was put in place.
With the work planned to start week commencing 12/02 a very extensive discussion was held with the main points highlighted below.
Toilet issues for staff on site, due to drainage, issue resolved Portaloo ordered £35 per week as variation. And also means no unlocking every morning.
Project was 4 weeks behind according to plan which with the current plan would run into at a minimum July-August. This was not acceptable.
The plan was revised in light of the time factor which will see the scaffolding going up on the North side of the Church in the near future. A new plan to be with the original requirements. With final completion and billing being 30th June.
As a result of all the discussions the project is being replanned and realigned as per the original guidelines.
The next major milestones
Roofers on site and starting work.
New guttering fitted
Strip down of the south roof.
Scaffolding on the North side to start.